A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost. If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then

Select one:

a. the FCAC is greater than the TBC.
b. the FCAC is less than the TBC.
c. the FCAC cannot be calculated with the values given.
d. additional information is needed to predict the FCAC.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 07:40
(a) what was the opportunity cost of non-gm food for many buyers before 2008? (b) why did they prefer the alternative? (c) what was the opportunity cost in 2008? (d) why did it change?
Answers: 3
question
Business, 22.06.2019 11:00
Factors like the unemployment rate,the stock market,global trade,economic policy,and the economic situation of other countries have no influence on the financial status of individuals. true or false
Answers: 1
question
Business, 22.06.2019 19:30
Which of the following constitute the types of unemployment occurring at the natural rate of unemployment? a. frictional and cyclical unemployment.b. structural and frictional unemployment.c. cyclical and structural unemployment.d. frictional, structural, and cyclical unemployment.
Answers: 2
question
Business, 22.06.2019 23:00
Abeverage company puts game pieces under the caps of its drinks and claims that one in six game pieces wins a prize. the official rules of the contest state that the odds of winning a prize are is the claim "one in six game pieces wins a prize" correct? why or why not? 1: 6.
Answers: 1
You know the right answer?
A third method for determining the forecasted cost at completion is to re-estimate the costs for all...
Questions
question
Mathematics, 21.06.2019 13:20