subject
Business, 12.03.2020 02:06 asorrell5075

An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m) = 2, and pessimistic (b) = 5. The activity’s expected duration is:

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:50
Your goal is to have $2,000,000. you have a total of $40,000 today. you invest the $40,000 and want to add to it each month. at 10% annual interest, how much do you need to invest each month in order to bring the total up to $2,000,000 30 years from now?
Answers: 2
question
Business, 21.06.2019 22:50
What happens when a bank is required to hold more money in reserve?
Answers: 3
question
Business, 22.06.2019 03:30
Acrosswalk_when there are no pavement markings.
Answers: 1
question
Business, 22.06.2019 05:30
Sally is buying a home and the closing date is set for april 20th. the annual property taxes are $1,234.00 and have not been paid yet. using actual days, how much will the buyer be credited and the seller be debited
Answers: 2
You know the right answer?
An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m)...
Questions
question
Mathematics, 15.10.2020 14:01
question
Mathematics, 15.10.2020 14:01