From the following list of activity bases for an automobile dealership, select the base that would be most appropriate for each of these costs:

1) preparation costs (cleaning, oil, and gasoline costs) for each car received
2) salespersons' commission of 5% of the sales price for each car sold
3) administrative costs for ordering cars

Number of cars sold
Dollar amount of cars ordered
Number of cars ordered
Number of cars on hand
Number of cars received
Dollar amount of cars sold
Dollar amount of cars received
Dollar amount of cars on hand

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 04:00
Wallis company manufactures only one product and uses a standard cost system. the company uses a predetermined plantwide overhead rate that relies on direct labor-hours as the allocation base. all of the company's manufacturing overhead costs are fixed—it does not incur any variable manufacturing overhead costs. the predetermined overhead rate is based on a cost formula that estimated $2,886,000 of fixed manufacturing overhead for an estimated allocation base of 288,600 direct labor-hours. wallis does not maintain any beginning or ending work in process inventory.
Answers: 2
question
Business, 22.06.2019 15:30
Brenda wants a new car that will be dependable transportation and look good. she wants to satisfy both functional and psychological needs. true or false
Answers: 1
question
Business, 22.06.2019 19:20
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to power a small isolated plant. assume we want to add a precompressor, which (when isolated and estimated separately) currently costs $13291. determine the total cost of the 120-kw unit. (hint: skip $ and comma symbols)
Answers: 3
question
Business, 22.06.2019 21:10
You are the manager of a large crude-oil refinery. as part of the refining process, a certain heat exchanger (operated at high temperatures and with abrasive material flowing through it) must be replaced every year. the replacement and downtime cost in the first year is $165 comma 000. this cost is expected to increase due to inflation at a rate of 7% per year for six years (i.e. until the eoy 7), at which time this particular heat exchanger will no longer be needed. if the company's cost of capital is 15% per year, how much could you afford to spend for a higher quality heat exchanger so that these annual replacement and downtime costs could be eliminated?
Answers: 1
You know the right answer?
From the following list of activity bases for an automobile dealership, select the base that would b...
Questions
question
Mathematics, 16.10.2019 21:00