To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity with: a. the largest cost slope on the critical path (CP)b. the smallest cost slope on the CP c. the largest cost slope not on the CP d. the smallest cost slope not on the CP

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 04:10
Oakmont company has an opportunity to manufacture and sell a new product for a four-year period. the company’s discount rate is 18%. after careful study, oakmont estimated the following costs and revenues for the new product: cost of equipment needed $ 230,000 working capital needed $ 84,000 overhaul of the equipment in year two $ 9,000 salvage value of the equipment in four years $ 12,000 annual revenues and costs: sales revenues $ 400,000 variable expenses $ 195,000 fixed out-of-pocket operating costs $ 85,000 when the project concludes in four years the working capital will be released for investment elsewhere within the company. click here to view exhibit 12b-1 and exhibit 12b-2, to determine the appropriate discount factor(s) using tables.
Answers: 2
question
Business, 22.06.2019 20:00
Which of the following statements is true of the balanced-scorecard? a. it is a more or less a one-dimensional metric of measuring competitive advantages of a firm. b. it is one of the traditional approaches of measuring firm performance. c. its primary focus is to base a firm's strategic goals entirely on external performance dimensions. d. it attempts to provide a holistic perspective on firm performance.
Answers: 1
question
Business, 23.06.2019 00:00
According to the video, the gross national product had declined from $104 billion in 1929 to about in 1933.
Answers: 2
question
Business, 23.06.2019 11:30
Which of the following is/are required to be in writing under the ucc's statute of frauds? a. a $10,000 oral contract dealing with specially manufactured goods. b. a $550 oral contract dealing with unique goods. c. a $100,000 oral contract involving the lease of goods where the defendant admits the existence of the contract in court. d. a $12,000 oral contract where the seller ships the goods and the buyer takes possession of half of the goods. e. all of the above.
Answers: 1
You know the right answer?
To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity w...
Questions
question
Mathematics, 05.02.2021 07:40
question
Mathematics, 05.02.2021 07:40
question
Mathematics, 05.02.2021 07:40