During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available. The contract is non-cancellable.

2020 2021 2022
Costs incurred to date $352,000 $726,000 $941,600
Estimated costs to complete 528,000 242,000 0
Billings to date (non-refundable) 264,000 792,000 1,408,000
Collections to date 237,600 712,800 1,254,000

a. Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
b. Prepare all necessary journal entries for 2021. (Use Materials, Cash, Payables for costs incurred to date.)

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
question
Business, 22.06.2019 20:40
Financial performance is measured in many ways. requirements 1. explain the difference between lag and lead indicators. 2. the following is a list of financial measures. indicate whether each is a lag or lead indicator: a. income statement shows net income of $100,000 b. listing of next week's orders of $50,000 c. trend showing that average hits on the redesigned website are increasing at 5% per week d. price sheet from vendor reflecting that cost per pound of sugar for the next month is $2 e. contract signed last month with large retail store that guarantees a minimum shelf space for grandpa's overloaded chocolate cookies for the next year
Answers: 2
question
Business, 22.06.2019 23:00
Acollege registrar's office requires you to first visit with one of three advisors and then with one of two financial professionals. this system best described as which of the following? a. single server, single phase systemb. multiple server multiphase systemc. multiple server, cross phase systemd. single server, multiphase systeme. multiple server, single phase system
Answers: 2
question
Business, 22.06.2019 23:50
The sarbanes-oxley act was passed to question 6 options: prevent fraud at public companies. replace all of the old accounting procedures with new ones. improve the accuracy of the company's financial reporting. both a and c
Answers: 3
You know the right answer?
During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job...
Questions
question
History, 10.02.2021 22:10