A construction project is broken down into the following 10 activities:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
1 — 5
2 1 2
3 1 5
4 1 6
5 2, 3 5
6 3 5
7 4 2
8 5 5
9 6, 7 6
10 8, 9 4

a. What is the critical path?
b. How many weeks will the project take to complete?
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 23:30
San ruiz interiors provides design services to residential and commercial clients. the residential services produce a contribution margin of $450,000 and have traceable fixed operating costs of $480,000. management is studying whether to drop the residential operation. if closed, the fixed operating costs will fall by $370,000 and san ruiz’ income will
Answers: 3
question
Business, 22.06.2019 05:50
Match the steps for conducting an informational interview with the tasks in each step.
Answers: 1
question
Business, 22.06.2019 08:30
What is the key to success in integrating both lethal and nonlethal activities during planning? including stakeholders once a comprehensive operational approach has been determined knowing the commander's decision making processes and "touch points" including stakeholders from the very beginning of the design and planning process including the liaison officers (lnos) in all the decision points?
Answers: 1
question
Business, 22.06.2019 09:00
Brian has been working for a few years now and has saved a substantial amount of money. he now wants to invest 50 percent of his savings in a bank account where it will be locked for three years and gain interest. which type of bank account should brian open? a. savings account b. money market account c. checking account d. certificate of deposit
Answers: 1
You know the right answer?
A construction project is broken down into the following 10 activities:

ACTIVITY IMMEDIA...
Questions