If a functional manager will not release the resources you need as project manager, your best course of action is to:
A) adjust project schedules and priorities accordingly.
B) try to negotiate for partial assistance.
C) notify top management of the consequences.
D) update your resume.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:40
You plan to invest some money in a bank account. which of the following banks provides you with the highest effective rate of interest? hint: perhaps this problem requires some calculations. bank 1; 6.1% with annual compounding. bank 2; 6.0% with monthly compounding. bank 3; 6.0% with annual compounding. bank 4; 6.0% with quarterly compounding. bank 5; 6.0% with daily (365-day) compounding.
Answers: 3
question
Business, 22.06.2019 11:00
Why are the four primary service outputs of spatial convenience, lot size, waiting time, and product variety important to logistics management? provide examples of competing firms that differ in the level of each service output provided to customers?
Answers: 1
question
Business, 22.06.2019 11:40
Select the correct answer brian wants to add a chart to his dtp project. what is the best way he can do this? a draw the chart using the dtp program draw option b create the chart in a spreadsheet then import it c. use the dtp chart wizard to create the chart within the dtp d. create an image of the chart in an image editor then import the image e use html code to create a chart within the dtp program
Answers: 3
question
Business, 22.06.2019 19:00
Read the scenario. alfonso is 19 years old and has a high school diploma. recently, he was promoted to assistant manager at the fast-food restaurant where he has worked since the age of sixteen. his dream is to become the restaurant’s manager. what is his best option for achieving his dream? he should find another job and work his way up to a higher position. he should hope that his manager transfers to another location and that he is his replacement. he should attend classes at the local college to receive training in management. he should work hard, work longer hours, and remain assistant manager.
Answers: 2
You know the right answer?
If a functional manager will not release the resources you need as project manager, your best course...
Questions
question
Mathematics, 15.07.2019 15:30