Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity/Time(weeks)

A:6weeks
B:7 weeks
C:3weeks
D:2weeks
E:4weeks
F:6weeks
G:10weeks
H:7weeks

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:30
Which p shifts to consumer in the four cs of the alternate marketing mix? a) promotion b) product c) place d) price
Answers: 3
question
Business, 22.06.2019 21:00
Haley photocopying purchases a paper from an out-of-state vendor. average weekly demand for paper is 150 cartons per week for which haley pays $15 per carton. in bound shipments from the vendor average 1000 cartoons with an average lead time of 3 weeks. haley operates 52 weeks per year; it carries a 4-week supply of inventory as safety stock and no anticipation inventory. the vendor has recently announced that they will be building a faculty near haley photocopying that will reduce lead time to one week. further, they will be able to reduce shipments to 200 cartons. haley believes that they will be able to reduce safety stock to a 1-week supply. what impact will these changes make to haley’s average inventory level and its average aggregated inventory value?
Answers: 1
question
Business, 23.06.2019 04:00
How do i make quick money as a 13 year.old with no alouence.
Answers: 1
question
Business, 23.06.2019 04:10
Which of the following would not be listed under cash outflows in a financial plan?
Answers: 2
You know the right answer?
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine....
Questions
question
Mathematics, 29.04.2021 06:40
question
Biology, 29.04.2021 06:40
question
History, 29.04.2021 06:40
question
Mathematics, 29.04.2021 06:40
question
Physics, 29.04.2021 06:40