Activity a has a duration of 3 days and begins on the morning of monday the 4th. the successor activity, b, has a finish-to-start relationship with a. the finish-to-start relationship has lag of 3 days, and activity b has a duration of 5 days. in case sunday is a nonworking day what can be determined from this data?
a. total elapsed days (completing both activities) is 7 days
b. activity b will be completed by the end of day on thursday, 14th
c. activity b will be completed by the end of day on friday, 15th.
d. activity b will be completed by the end of day on tuesday, 12th
Answers: 3
Business, 23.06.2019 02:40
If a country is looking to increase economic growth quickly, it should: choose the correct answer from the following choices, and then select the submit answer button. answer choices focus on natural resources and develop physical capital. make investments from domestic savings and adopt new technology. increase spending on human capital and start a new political approach. develop new technologies funded by the public sector.
Answers: 1
Business, 23.06.2019 07:30
What criteria does a company have to meet to be considered a monopoly?
Answers: 2
Business, 23.06.2019 11:20
In a hypothetical economy, a market basket consists of one laptop and two dvd players. in the base year, 2010, the price of a dvd player was $200, and the price of a laptop was $500. in 2015, the price of a dvd player was $380, and the price of a laptop was $750. the cpi for 2010 was
Answers: 3
Activity a has a duration of 3 days and begins on the morning of monday the 4th. the successor activ...
French, 21.10.2020 22:01
Mathematics, 21.10.2020 22:01
Computers and Technology, 21.10.2020 22:01
Mathematics, 21.10.2020 22:01
Advanced Placement (AP), 21.10.2020 22:01
Mathematics, 21.10.2020 22:01
Mathematics, 21.10.2020 22:01
Mathematics, 21.10.2020 22:01
English, 21.10.2020 22:01
Physics, 21.10.2020 22:01
Mathematics, 21.10.2020 22:01