Planned value is:

a. the cumulative total costs incurred in accomplishing the various project work packages.
b. the real budgeted value of the work that has actually been performed to date.
c. a cost estimate of the budgeted resources across the project's life cycle.
d. the total budget for the project.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 01:00
Need with my trade theory homework. i doubt what i wrote was right.consider a monopolistically competitive market for soft drinks in which n symmetric firms face the following demand function: q=s(1/n-b(p-(p with the straight line on which implies the marginal revenue functionmr=p-(q/sb)finally, suppose firms face the total cost functiontc=900,000+100qsuppose the market size, s, is 27,000,000, and the elasticity parameter b is 0.003.diagram the price and the average total cost in the market as a function of the number of firms. what are the equations for each curve, and why does each curve slope up or down? label the equilibrium number of firms and the equilibrium price in the diagram. why is this the equilibrium?
Answers: 1
question
Business, 22.06.2019 04:00
Don’t give me to many notifications because it will cause you to lose alot of points
Answers: 1
question
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
question
Business, 22.06.2019 16:40
Job 456 was recently completed. the following data have been recorded on its job cost sheet: direct materials $ 2,418 direct labor-hours 74 labor-hours direct labor wage rate $ 13 per labor-hour machine-hours 137 machine-hours the corporation applies manufacturing overhead on the basis of machine-hours. the predetermined overhead rate is $14 per machine-hour. the total cost that would be recorded on the job cost sheet for job 456 would be: multiple choice $3,380 $5,298 $6,138 $2,622
Answers: 1
You know the right answer?
Planned value is:

a. the cumulative total costs incurred in accomplishing the various...
Questions