You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you have a large budget for the project, you are considering crashing activity a2, which has the potential to shorten the time of a2 by 3 days.
what do you think about this opportunity?
o a good idea, it will reduce the project duration by 3 days.
o a bad idea, as a2 is not on the critical path.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:20
Trinity coatings company uses the indirect method to prepare its statement of cash flows. refer to the following information for 2018: the beginning balance in the cash account was $ 3 comma 000. net cash provided by operating activities: $ 42 comma 000 net cash used for investing activities: $(26 comma 500) net cash provided by financing activities: $ 1 comma 700 the statement of cash flows will show
Answers: 2
question
Business, 22.06.2019 02:30
Acompany factory is considered which type of resource a.land b.physical capital c.labor d.human capital
Answers: 2
question
Business, 22.06.2019 06:30
"in my opinion, we ought to stop making our own drums and accept that outside supplier's offer," said wim niewindt, managing director of antilles refining, n.v., of aruba. "at a price of $21 per drum, we would be paying $4.70 less than it costs us to manufacture the drums in our own plant. since we use 70,000 drums a year, that would be an annual cost savings of $329,000." antilles refining's current cost to manufacture one drum is given below (based on 70,000 drums per year):
Answers: 1
question
Business, 22.06.2019 20:20
An economic theory that calls for workers to take control of factories is .
Answers: 3
You know the right answer?
You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you ha...
Questions