Abc construction has developed the following set of activities for its budgeting process.

activity

predecessor

normal activity time (days)

resulting activity time if activity is crashed (days)

total cost to complete activity in normal time

total cost to complete activity in crash time

a

--

4

2

$200

$600

b

a

6

3

$300

$1200

c

a

4

1

$300

$900

d

b, c

3

2

$500

$550

e

d

4

1

$500

$1700

a) using the normal times, what is the critical path and project completion time for the budgeting process? also, what is the cost to complete the project based on the normal times?

b) if we want to reduce the project completion time to the minimum possible time by crashing activities, what is the new project completion time and what is the new total project cost?

c) modify the problem as follows. there is now an indirect cost of $75 per day, which is in addition to the cost identified above. there is also a penalty cost of $200 per day for any project completion time over 11 days. what is the minimum cost schedule for the project and what is the total cost for this schedule? identify what are the time and the path of this minimum cost schedule.

d) suppose that the company wants to crash the project 4 days. based on the information provided in the table and in part c) and the results from part c), what would the minimum penalty cost have to be for this to be supported by the economics in the problem? assume that the indirect cost remains at $75 per day.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 22:30
Abusiness cycle reflects in economic activity, particularly real gdp. the stages of a business cycle
Answers: 2
question
Business, 22.06.2019 12:50
Two products, qi and vh, emerge from a joint process. product qi has been allocated $34,300 of the total joint costs of $55,000. a total of 2,900 units of product qi are produced from the joint process. product qi can be sold at the split-off point for $11 per unit, or it can be processed further for an additional total cost of $10,900 and then sold for $13 per unit. if product qi is processed further and sold, what would be the financial advantage (disadvantage) for the company compared with sale in its unprocessed form directly after the split-off point?
Answers: 2
question
Business, 22.06.2019 20:20
Tl & co. is following a related-linked diversification strategy, and soar inc. is following a related-constrained diversification strategy. how do the two firms differ from each other? a. soar inc. generates 70 percent of its revenues from its primary business, while tl & co. generates only 10 percent of its revenues from its primary business. b. soar inc. pursues a backward diversification strategy, while tl & co. pursues a forward diversification strategy. c. tl & co. will share fewer common competencies and resources between its various businesses when compared to soar inc. d. tl & co. pursues a differentiation strategy, and soar inc. pursues a cost-leadership strategy, to gain a competitive advantage.
Answers: 3
question
Business, 22.06.2019 22:00
What resourse is both renewable and inexpensive? gold coal lumber mineral
Answers: 1
You know the right answer?
Abc construction has developed the following set of activities for its budgeting process.

Questions
question
Mathematics, 14.01.2021 19:50
question
Biology, 14.01.2021 19:50
question
Social Studies, 14.01.2021 19:50