In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
a. smallest duration
b. least slack
c. most slack
d. lowest identification number
e. highest cost

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 02:50
Grey company holds an overdue note receivable of $800,000 plus recorded accrued interest of $64,000. the effective interest rate is 8%. as the result of a court-imposed settlement on december 31, year 3, grey agreed to the following restructuring arrangement: reduced the principal obligation to $600,000.forgave the $64,000 accrued interest.extended the maturity date to december 31, year 5.annual interest of $40,000 is to be paid to grey on december 31, year 4 and year 5. the present value of the interest and principal payments to be received by grey company discounted for two years at 8% is $585,734. grey does not elect the fair value option for reporting the debt modification. on december 31, year 3, grey would recognize a valuation allowance for impaired loans of
Answers: 3
question
Business, 22.06.2019 21:00
At present, the united states has an embargo against north korea because a. the two countries have extremely poor political relations. b. north korea will not adopt a capitalist government. c. north korean products are too difficult to use. d. north korea has an embargo on american products. e. products from north korea are in higher demand than american-made products.
Answers: 2
question
Business, 23.06.2019 00:00
How much is a 2019 tesla? ? exact price trying to buy for my 6 year old sister
Answers: 2
question
Business, 23.06.2019 01:50
You are looking at a one-year loan of $16,500. the interest rate is quoted as 8.7 percent plus two points. a point on a loan is 1 percent (one percentage point) of the loan amount. quotes similar to this one are common with home mortgages. the interest rate quotation in this example requires the borrower to pay two points to the lender up front and repay the loan later with 8.7 percent interest. what rate would you actually be paying here?
Answers: 3
You know the right answer?
In a resource-constrained project, the first priority in assigning resources is usually given to act...
Questions
question
Mathematics, 23.02.2022 14:00
question
Mathematics, 23.02.2022 14:00