If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to finish on schedule?

a. 680
b. 650
c. 620
d. 580

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:00
What is credit and debit in accounting
Answers: 2
question
Business, 22.06.2019 01:30
Diversity is an obstacle all marketers face: true false
Answers: 2
question
Business, 22.06.2019 17:00
Serious question, which is preferred in a business? pp or poopoo?
Answers: 1
question
Business, 22.06.2019 20:30
The smelting department of kiner company has the following production and cost data for november. production: beginning work in process 3,700 units that are 100% complete as to materials and 23% complete as to conversion costs; units transferred out 10,500 units; and ending work in process 8,100 units that are 100% complete as to materials and 41% complete as to conversion costs. compute the equivalent units of production for (a) materials and (b) conversion costs for the month of november.
Answers: 3
You know the right answer?
If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products w...
Questions