subject
Arts, 18.05.2021 05:30 taiyana74

XYZ Ltd signs a contract on 30 June 2015, agreeing to build a bridge for ABC Limited at a contract price of $40 million. XYZ Ltd estimates that construction costs will be as follows:

Year Ending Cost

30 June 2016 $10 000 000
30 June 2017 $16 000 000
30 June 2018 $ 6 000 000
$32 000 000
The contract provides that ABC will make payments on 30 June of each year as follows:
2016 $8 000 000
2017 $20 000 000
2018 $12 000 000
$40 000 000
XYZ now estimates at the beginning of the 2017 financial year that construction costs will be
as follows:

Year Ending Cost

30 June 2016 $10 000 000
30 June 2017 $21 000 000
30 June 2018 $15 000 000
$46 000 000
Required:
Calculate:
a) Percentage of completion for each of the three years. (4 marks)
b) Revenue to be recognised in each of the three years. (3 marks)
c) Gross profit/loss to be recognised in each of the three years. (3 marks)

ansver
Answers: 2

Another question on Arts

question
Arts, 22.06.2019 23:30
Which of these is a consistent periodic pulse separated into equivalent intervals of time?
Answers: 3
question
Arts, 25.06.2019 00:30
Which of the following “masters” can be earned without attending a college or university? set design costume design sound engineering carpentry
Answers: 1
question
Arts, 25.06.2019 11:30
This sculpture from the hellenistic period is entitled
Answers: 2
question
Arts, 25.06.2019 14:20
Agirl ! what specific south african performance practice did ladysmith black mambazo use?
Answers: 1
You know the right answer?
XYZ Ltd signs a contract on 30 June 2015, agreeing to build a bridge for ABC Limited at a contract...
Questions
question
Health, 07.02.2022 03:10
question
Mathematics, 07.02.2022 03:10
question
Mathematics, 07.02.2022 03:10